As in 2015 (GVV-14-BXL), Gijs Van Vaerenbergh designed a temporary bridge over the Canal using crane elements, which this time remains in place throughout the summer. The bridge represents an upgrade of its predecessor: the span is longer (55 m instead of 45 m), the kink in the bridge has been shifted off-center to relieve the largest moment sections, and heavier crane elements were used to achieve a greater clearance height. This last modification introduces an entirely new structural challenge. The diagonals do not run parallel within the two vertical planes but rotate around the bridge’s central axis, resulting in different force distributions in the two vertical planes, which behave as beams. The custom connection at the kink forms a zigzag line, aligned with the elements it joins. At the bridge ends, only two frames are required to connect the elements and transfer the loads via stacked concrete counterweights to the quay.