project
architect
dmvA architecten
period
2006 - 2010
budget
€ 2.100.000,00
surface area
2.400 m2
client
stad Mechelen
status
finished

All existing concrete floors were assessed for their load-bearing capacity and, in most cases, replaced or reinforced with a composite cast-in-place topping. The introduction of new voids and stair openings, the removal of existing columns, the addition of timber-framed volumes on the roof, and the revised floor plan required a comprehensive renovation of the existing structure. In certain areas, the foundation also needed reinforcement using micropiles. On the street side, a new building volume was constructed, providing a passageway to the newly created inner courtyard.