project
architect
Architecten De Vylder Vinck Taillieu
period
2006 - 2008
budget
€ 220.000,00
surface area
620 m2
client
Toneelhuis
status
finished

The new load-bearing floors consist of solid glued timber planks placed vertically against each other. The planks were oversized to ensure sufficient fire resistance. In the production studios, the existing columns needed to be removed; this was addressed by temporarily supporting the structure before cutting the columns.